Mitasny roadmap

# Task Status Work remaining Est. finish date
9 Generate weekly report Finished 0 11-22
10 Continuing-status Finished 0 11-22
11 Chart header to include dates Finished 0 11-22
12 Project CRUD Finished 0 11-22
13 User registration Finished 0 11-22
14 Reorder tasks Finished 0 11-22
15 Weekly report containing all projects Ongoing 1 11-25
16 SSL encryption Pending 1 11-26
17 Django allauth Pending 2 11-28
18 Add task to beginning Pending 1 11-29
19 Mark task as done Pending 1 12-02
20 Confirm that finished tasks have zero work remaining Pending 1 12-03
21 About page Pending 1 12-04
23 Option to show descriptions in task list Pending 1 12-05
24 Send weekly report as email Pending 3 12-10
25 Script to take screenshots of graphs Pending 1 12-11
26 Include graph screenshots in mail Pending 1 12-12
Total: 2 week(s), 4 day(s) 14 12-12