Mitasny roadmap

# Task Status Work remaining Est. finish date
9 Generate weekly report Finished 0 08-10
10 Continuing-status Finished 0 08-10
11 Chart header to include dates Finished 0 08-10
12 Project CRUD Finished 0 08-10
13 User registration Finished 0 08-10
14 Reorder tasks Finished 0 08-10
15 Weekly report containing all projects Ongoing 1 08-11
16 SSL encryption Pending 1 08-12
17 Django allauth Pending 2 08-14
18 Add task to beginning Pending 1 08-17
19 Mark task as done Pending 1 08-18
20 Confirm that finished tasks have zero work remaining Pending 1 08-19
21 About page Pending 1 08-20
23 Option to show descriptions in task list Pending 1 08-21
24 Send weekly report as email Pending 3 08-26
25 Script to take screenshots of graphs Pending 1 08-27
26 Include graph screenshots in mail Pending 1 08-28
Total: 2 week(s), 4 day(s) 14 08-28